home *** CD-ROM | disk | FTP | other *** search
/ Apple Reference & Presen…rary 6 (Reseller Edition) / Apple Ref. & Pres. Lib.v6.0.toast / pc / 5-Fonts & Software / Applications / MacProject II / MacProject II Help / card_38957.txt < prev    next >
Text File  |  1989-09-27  |  2KB  |  69 lines

  1. -- card: 38957 from stack: in
  2. -- bmap block id: 0
  3. -- flags: 0000
  4. -- background id: 3633
  5. -- name: Task and Resource Durations 2
  6.  
  7.  
  8. -- part 37 (field)
  9. -- low flags: 01
  10. -- high flags: 0002
  11. -- rect: left=409 top=260 right=275 bottom=464
  12. -- title width / last selected line: 0
  13. -- icon id / first selected line: 0 / 0
  14. -- text alignment: 1
  15. -- font id: 3
  16. -- text size: 10
  17. -- style flags: 0
  18. -- line height: 13
  19. -- part name: pagexofy
  20.  
  21.  
  22. -- part 38 (button)
  23. -- low flags: 00
  24. -- high flags: A003
  25. -- rect: left=245 top=166 right=187 bottom=444
  26. -- title width / last selected line: 0
  27. -- icon id / first selected line: 0 / 0
  28. -- text alignment: 1
  29. -- font id: 3
  30. -- text size: 10
  31. -- style flags: 0
  32. -- line height: 13
  33. -- part name: Changing the Critical Path Threshold
  34. ----- HyperTalk script -----
  35. on mouseUp
  36.   go card id 61529
  37. end mouseUp
  38.  
  39.  
  40. -- part contents for background part 6
  41. ----- text -----
  42. MacProject II compares all the task and resource durations for each task and uses the longest of these to calculate the project schedule. The longest durations are said to 
  43. ‚Äúdrive‚Äù the schedule. 
  44.  
  45. If a resource duration is driving the schedule, the number representing the duration and the name of the resource are underlined in the Schedule Chart, Project Table, and Task Info window. The calendar for that resource becomes the calendar for the task.
  46.  
  47.  
  48. -- part contents for background part 7
  49. ----- text -----
  50. Durations can be measured in minutes, hours, days, weeks, or months. These are called the units of duration, or duration scale. The unit of duration is used in many other parts of the project, too, including lag times, critical path threshold, and resource costs.
  51.  
  52.  
  53.  
  54.  
  55.  
  56.  
  57.  
  58.  
  59. -- part contents for background part 27
  60. ----- text -----
  61. Schedule Information
  62.  
  63. -- part contents for background part 28
  64. ----- text -----
  65. Task & Resource Durations
  66.  
  67. -- part contents for card part 37
  68. ----- text -----
  69. 2 of 2